Administrative Record - Congaree River

The documents listed below are included in DHEC's Administrative Record for the assessment and cleanup alternatives evaluated for the Congaree River sediments. These documents include investigation activities, sampling results, work plans, and cost analyses.

Interested persons are encouraged to review these documents to learn more about this site.

Date Title Description
October 5, 2023 Certification of Completion - Area 2 Cofferdam  
October 4, 2023 Letter to DHEC Requesting Certification of Completion - Area 2 Cofferdam  
August 8, 2023 Certification of Completion - Area 1 Cofferdam  
August 4, 2023 Letter to DHEC Requesting Certification of Completion - Area 1 Cofferdam  
May 26, 2022 DHEC Approval of Modified Removal Action Work Plan  
May 20, 2022 DHEC Approval of Entact's Alternate Approach to Cofferdam Liner Material & Reinforcement  
May 18, 2022 Entact's Alternate Approach to Cofferdam Liner Material & Reinforcement  
May 12, 2022

Modified Removal Action Work Plan 

 
May 9, 2022 DHEC's Approval of the April 2022 Monthly Project Update  
May 8, 2022 Dominion Energy's April 2022 Monthly Project Update  
May 4, 2022 Approval of 1st Quarter 2022 Quarterly Report DHEC Approval of Dominion Energy's 1st Quarter 2022 Report
May 2, 2022 Approval of the March 2022 Mussel Relocation Initial Reconnaissance Survey  
May 1, 2022 Quarterly Report 1st Quarter 2022 Dominion Energy's 1st Quarter 2022 Report - Significant Activities & Milestones
April 11, 2022 Dominion Energy's March 2022 Mussel Relocation Initial Reconnaissance Survey  
March 31, 2022 DHEC's Approval of Diving Safe Practices Manual  
March 31, 2022 DHEC's Approval of Dominion Energy's Final Work Plan for Munitions Response  
March 31, 2022 DHEC's Approval of Dominion Energy's Final Diving Operations Plan  
March 31, 2022 DHEC's Approval of Dominion Energy's Final Explosives Safety Plan Munitions  
  Diving Safe Practices Manual  
  Dominion Energy's Final Diving Operations Plan  
  Dominion Energy's Final Explosives Safety Plan  
  Dominion Energy's Final Work Plan for Munitions Response  
  Army Corps and Dominion Energy Memorandum of Agreement  
March 16, 2022 Army Corps Recertification of the Nationwide Permit  
March 10, 2022 Dominion Energy's Senate Street Pavement Investigation Report   
March 3, 2022 Approval of 4th Quarter 2021 Quarterly Report DHEC Approval of Dominion Energy's 4th Quarter 2021 Report
March 2, 2022 Quarterly Report 4th Quarter 2021 Dominion Energy's 4th Quarter 2021 Report - Significant Activities & Milestones
February 25, 2022 Dominion Energy's Recertification Joint Federal and State Application Dominion Energy's recertification of Joint Federal and State Application
February 25, 2022 Dominion Energy Letter Requesting Recertification of Joint Federal & State Application  Dominion Energy Letter requesting recertification of the Joint Federal and State Application for the Stakeholder-Developed Modified Removal Action
February 15, 2022 DHEC's Action Memorandum on the Modified Removal Action  
December 23, 2021 DHEC's Authorization to Construct Under the General Permit  
December 10, 2021 Department of the Army Nationwide Permit Verification  
October 25, 2021 Approval of 3rd Quarter 2021 Quarterly Report DHEC Approval of Dominion Energy's 3rd Quarter 2021 Report
October 22, 2021 DE's Confirmation to USACE Removal Action Dominion Energy's Confirmation to the US Army Corp of the Removal Action as the Path Forward.
October 22, 2021 Quarterly Report 3rd Quarter 2021 Dominion Energy's 3rd Quarter 2021 Report - Significant Activities & Milestones
October 20, 2021 DHEC's Concurrence Letter - USACE's MOA for SMRA. DHEC's Concurrence Letter with finalizing the US Army Corps of Engineers' historic properties MOA for the Stakeholder Modified Removal Action.
September 23, 2021 DHECs approval of Dominion Energy's Response to Comments on the UXO Plans  
August 25, 2021 Dominion Energy's Response to Comments on the UXO Plans  
August 9, 2021 Approval of Quarterly Report for 1st & 2nd Quarter of 2021 DHEC Approval of Dominion Energy's 1st & 2nd Quarter 2021 Report
August 5, 2021 Quarterly Report for 1st & 2nd Quarter of 2021 Dominion Energy's 1st & 2nd Quarter 2021 Report - Significant Activities/Milestones/Schedule
April 27, 2021 DHEC Comments on UXO Plans  
February 26, 2021 Updated Unexploded Ordnance (UXO) Plans
January 28, 2021 Quarterly Report for 4th Quarter 2020 Dominion Energy's 4th Quarter 2020 Report - Significant Activities/Milestones/Schedule
December 15, 2020 Dominion Energy's Response to USACE Additional Information Request Cover Letter Dominion Energy's Response to USACE Additional Information Request Cover Letter
  Dominion Energy's Response to USACE Additional Information Request - Enclosure #2 Dominion Energy South Carolina, Inc. Congaree River Easement 
Georgia Aster and Smooth Coneflower Survey Columbia, South Carolina 
  Dominion Energy's Response to USACE Additional Information Request - Enclosure #1 Memorandum of Agreement
October 27, 2020 USACE Additional Information Request  USACE Request for Additional Information on the Permit Application
October 21, 2020 DNR Comments on Permit Application  
October 6, 2020 Weekly Status Report Week Ending 9/30/2020 Congaree River Project Weekly Status Report for Week Ending September 30, 2020
September 30, 2020 Weekly Status Report Week Ending 9/25/2020 Congaree River Project Weekly Status Report for Week Ending September 25, 2020
September 28, 2020 Joint Application Attachment C Approval DHEC's written approval of Dominion Energy's USACE Permit Submittal Attachment C.
September 28, 2020 Attachment C Attachment C - Part 1
Attachment C - Part 2
Attachment C - Part 3
Attachment C - Part 4
Attachment C - Part 5
September 28, 2020 Attachment C - Project Description Dominion Energy's USACE Permit Submittal Attachment C - Project Description
September 23, 2020 Weekly Status Report Week Ending 9/18/2020 Congaree River Project Weekly Status Report for Week Ending September 18, 2020
September 21, 2020 Joint Application Attachment P Approval DHEC's written approval of Dominion Energy's USACE Permit Submittal Attachment P. 
September 21, 2020 Joint Application Attachment K Approval DHEC's written approval of Dominion Energy's USACE Permit Submittal Attachment K. 
September 21, 2020 Joint Application Attachment L Approval DHEC's written approval of Dominion Energy's USACE Permit Submittal Attachment L. 
September 21, 2020 Joint Application Attachment M Approval DHEC's written approval of Dominion Energy's USACE Permit Submittal Attachment M. 
September 18, 2020 Attachment L - Historic and Archaeological Properties Identification Dominion Energy's USACE Permit Submittal Attachment L - Historic and Archaeological Properties Identification
September 18, 2020 Attachment M - Cultural Resource Identification Survey, Archaeological Data Recovery Plan, Updated Date Recovery License, and a draft Memorandum of Agreement Dominion Energy's USACE Permit Submittal Attachment M - Cultural Resource Identification Survey, Archaeological Data Recovery Plan, Updated Date Recovery License, and a draft Memorandum of Agreement.
September 18, 2020 Attachment P - Restoration - Operation, Maintenance and Monitoring Plan Dominion Energy's USACE Permit Submittal Attachment P - Restoration - Operation, Maintenance and Monitoring Plan
September 16, 2020 Weekly Status Report Week Ending 9/11/2020 Congaree River Project Weekly Status Report for Week Ending September 11, 2020
September 10, 2020 Attachment K -  Stormwater Management & Sediment Control Plan for Modified Removal Action Dominion Energy's USACE Permit Submittal Attachment K - Stormwater Management & Sediment Control Plan for Modified Removal Action
September 9, 2020 Weekly Status Report Week Ending 9/04/2020 Congaree River Project Weekly Status Report for Week Ending September 4, 2020
September 2, 2020 Dominion Energy's Response to USACE Additional Information Request - Enclosure #5 DHEC Approval Letter for the FDP Work Plan
September 1, 2020 Joint Application Attachment H Approval DHEC's written approval of Dominion Energy's USACE Permit Submittal Attachment H. 
September 1, 2020 Attachment H - Mussel Relocation Plan Dominion Energy's USACE Permit Submittal Attachment H - Mussel Relocation Plan. 
August 31, 2020 Joint Application Attachment G Approval DHEC's written approval of the Joint Application Attachment G (Draft Navigation Plan and United States Coast Guard (USCG) Application).
August 31, 2020 Joint Application Attachments D, E, & F Approval DHEC's written approval of the Joint Application Attachments D (Wetland and Stream Delineation Report), E (Name and Addresses of Adjacent Property Owners), and F (Other Permits and Approvals or Denials)
August 26, 2020 Weekly Status Report Week Ending 8/21/2020 Congaree River Project Weekly Status Report for Week Ending August 21, 2020
August 20, 2020 Attachment G - Draft Navigation Plan w/USCG Application Draft Navigation Plan and United States Coast Guard (USCG) Application that will be included as Attachment G in the United States Army Corps of Engineers (USACE) permit application that will be submitted by September 30, 2020.
August 19, 2020 Weekly Status Report Week Ending 8/14/2020 Congaree River Project Weekly Status Report for Week Ending August 14, 2020
August 29, 2020 Joint Application Attachments D, E, & F Attachments D (Wetland and Stream Delineation Report), E (Name and Addresses of Adjacent Property Owners), and F (Other Permits and Approvals or Denials) that will be included in the United States Army Corps of Engineers (USACE) permit application that will be submitted by September 30, 2020.
August 14, 2020 Joint Application Attachments A & B Approval DHEC's written approval of the Joint Application Attachment A (NWP 38 Checklist) and Attachment B (Cofferdam Design Drawings).
August 12, 2020 Weekly Status Report Week Ending 8/07/2020 Congaree River Project Weekly Status Report for Week Ending August 7, 2020
August 7, 2020 Weekly Status Report Week Ending 7/31/2020 Congaree River Project Weekly Status Report for Week Ending July 31, 2020
August 5, 2020 Approval of List of Attachments DHEC's written approval of Dominion Energy's USACE Permit Application List of Attachments.
August 5, 2020 USACE Permit Application - List of Attachments List of attachments from Dominion Energy that will accompany the actual 3-page permit application that will be submitted to the United States Army Corps of Engineers (USACE) by September 30, 2020.
August 3, 2020 Joint Application Attachment A & Attachment B  Attachments A (Draft Nationwide Permit 38 Checklist)  and B (Cofferdam Design Drawings).
July 31, 2020 Weekly Status Report Week Ending 7/24/2020 Congaree River Project Weekly Status Report for Week Ending July 24, 2020
July 31, 2020 Approval of Surface Water Assessment DHEC's written approval of Dominion Energy's Surface Water Assessment
July 31, 2020 Surface Water Assessment Dominion Energy's Surface Water Assessment Report – June 2020 Sampling Event
July 23, 2020 Weekly Status Report Week Ending 7/17/2020` Congaree River Project Weekly Status Report for Week Ending July 17, 2020
July 17, 2020 Weekly Status Report Week Ending 7/10/2020 Congaree River Project Weekly Status Report for Week Ending July 10, 2020
July 9, 2020 Rockfill Cofferdam Slope Stability Analysis Approval DHEC's Written Approval of the Rockfill Cofferdam Slope Stability Analysis 
July 9, 2020 Reinforced Rockfill Cofferdam Conceptual Design Approval DHEC's Written Approval of the Reinforced Rockfill Cofferdam Conceptual Design
July 8, 2020 Weekly Status Report Week Ending 7/3/2020 Congaree River Project Weekly Status Report for Week Ending July 3, 2020
July 1, 2020 Weekly Status Report Week Ending 6/26/2020 Congaree River Project Weekly Status Report for Week Ending June 26, 2020
June 24, 2020 Weekly Status Report Week Ending 6/19/2020 Congaree River Project Weekly Status Report for Week Ending June 19, 2020
June 19, 2020 Weekly Status Report Week Ending 6/12/2020 Congaree River Project Weekly Status Report for Week Ending June 12, 2020
June 17, 2020 Low Flow Sensitivity Analysis Approval  DHEC's Written Approval of the Low Flow Sensitivity Analysis
June 10, 2020 Congaree River Low Flow Sensitivity Analysis WSP USA's Low Flow Sensitivity Analysis of the Congaree River
June 10, 2020 Weekly Status Report Week Ending 6/5/2020 Congaree River Project Weekly Status Report for Week Ending June 5, 2020
June 8, 2020 River Bottom Erosion Potential Evaluation Approval DHEC's Written Approval of the River Bottom Erosion Potential Evaluation 
June 8, 2020 West Bank Erosion Potential Evaluation Approval DHEC's Written Approval of the West Bank Erosion Potential Evaluation
June 3, 2020 Weekly Status Report Week Ending 5/29/20 Congaree River Project Weekly Status Report for Week Ending May 29, 2020
May 21, 2020 Comments on Revised Permit Application Strategy DHEC Comments on Revised Permit Application Strategy
April 27, 2020 Review of 1st Quarter 2020 Report DHEC Review of Dominion Energy's 1st Quarter 2020 Report 
April 27, 2020 Quarterly Report for 1st Quarter 2020 Dominion Energy's 1st Quarter 2020 Report - Significant Activities/Milestones/Schedule
April 21, 2020 Revised Permit Application Strategy Revised Permit Application Strategy from Dominion Energy
April 10, 2020 Approval of Reinforced Rockfill Berm Approach DHEC Letter of Approval  to Dominion Energy of Reinforced Rockfill Berm Approach
April 7, 2020 Letter Requesting Revised Permit Application Strategy DHEC Letter to Dominion Energy requesting Revised Permit Application Strategy
April 7, 2020 Lexington County Concurrence Letter Lexington County Concurrence Letter on No Rise No Impact Certification
March 31, 2020 Richland County Concurrence Letter Richland County Concurrence Letter on No Rise No Impact Certification
March 10, 2020 River Bottom Erosion Potential Evaluation WSP USA's River Bottom Erosion Potential Evaluation of the of the Congaree River
February 24, 2020 Quarterly Report for 4th Quarter 2019 Dominion Energy's 4th Quarter 2019 Report  - Significant Activities/Milestones/Schedule
November 26, 2019 West Bank Erosion Potential Evaluation WSP USA's West Bank Erosion Potential Evaluation of the of the Congaree River
October 15, 2019 Quarterly Report for 3rd Quarter 2019 Dominion Energy's 3rd Quarter 2019 Report  - Significant Activities/Milestones/Schedule
October 9, 2019 No Rise Certification sent to Local Floodplain Managers No Rise Certification sent to Local Floodplain Managers
October 4, 2019 USACE Concurrence with MRA Conceptual Plan  U.S. Army Corps of Engineers Concurrence with Modified Removal Action Conceptual Plan
August 28, 2019 Dominion Energy's Response to USACE email  Dominion Energy's Response to U.S. Army Corps of Engineers email from 08-08-19
July 24, 2019 Permit Application Strategy
 
Dominion Energy's Permit Application Strategy
 
July 19, 2019 Review of Semiannual Surface Water Assessment Report
 
DHEC's Review of the Semi-Annual Surface Water Assessment Report
 
July 1, 2019 Quarterly Report for 2nd Quarter 2019
 
Dominion Energy's 2nd Quarter 2019 Report
 
June 26, 2019 4th Semiannual Surface Water Assessment Report
 
Dominion Energy's 4th Semi-Annual Surface Water Assessment Report
April 12, 2019 No Rise Certification
 
Dominion Energy's No Rise Certification for the Modified Removal Action Cofferdam Footprint
April 12, 2019 Hydraulic Analysis Report Dominion Energy's Hydraulic Backwater Analysis for the Modified Removal Action Cofferdam Footprint
April 2, 2019 Quarterly Report 1st Quarter 2019: Significant Milestones SCE&G's Quarterly Report on progress made and significant milestones reached during 1st Quarter 2019
February 8, 2019 Review: Conceptual Plan for a Modified Removal Action DHEC's Approval of Modified Removal Action as preferred path forward along with stakeholder support statements
December 18, 2018 Conceptual Plan for a Modified Removal Action SCANA's Summary of the Modified Removal Action that Stakeholders agreed to on November 15, 2018
October 23, 2018 Review: Preliminary Removal Action Work Plan DHEC's Response to Preliminary Removal Action Work Plan
September 18, 2018 Preliminary Removal Action Work Plan SCANA's Updated Removal Action Work Plan
July 31, 2018 Removal Action Alternative DHEC’s request for SCANA to submit an updated work plan for the removal of tar-like material.
June 22, 2018 Removal Action Alternative Letter from DHEC to SCANA requesting them to evaluate the potential for a modified removal action
May 23, 2018 Corps Response to SCE&G dated May 19, 2018 with Enclosures USACOE response to SCANA’s Letter.
May 23, 2018 Review: Second Semi-Annual Surface Water Assessment Report DHEC’s review of the Surface Water Monitoring Report
May 8, 2018 Second Semi-Annual Surface Water Assessment Report Surface Water Monitoring Report
April 13, 2018 US EPA Letter to Mayor Benjamin Concerning Site Cleanup Letter from US EPA to Mayor Benjamin
March 27, 2018 Letter from Mayor Benjamin to  US EPA Administrator Letter from Mayor Benjamin to US EPA Administrator Scott Pruitt
March 26, 2018 Guignard’s Request to Participate in Remedial Measures Discussion Letter from Guignard Associates, LLC, property owner on eastern bank, requesting to be included in site remedial discussions.
March 22, 2018 Response Regarding Letter of 3/19/2018 Southern Environmental Law Center’s response to SCANA’s letter to USACOE.
March 19, 2018 Cofferdam Approach for a Remedial Action Letter from SCANA to USACOE requesting additional information on a modified removal action alternative
December 7, 2017 Under Review: Draft Sediment Capping Work Plan Letter from DHEC to Congaree River Keeper outlining that the capping plan has been received and is currently under review.
November 30, 2017 Draft Sediment Capping Work Plan with Appendices SCANA’s work plan for capping the coal tar in the river
November 27, 2017 Review: First Semi-Annual Surface Water Assessment Report DHEC’s Review of the Surface Water Assessment Report
November 7, 2017 First Semi-Annual Surface Water Assessment Report Surface Water Assessment Report
October 18, 2017 USACOE Nationwide Permit (NWP 38) USACOE approval of the Nationwide Permit for Capping the river
October 5, 2017 Review: GW Monitoring Report, June 2017 Letter from Cassidy to SCANA
September 20, 2017 GW Monitoring Report, June 2017 Groundwater Monitoring Report
August 9, 2017 Letter from DHEC to Riverkeeper with Aquatic Macroinvertebrate Study Attachment Letter from DHEC to Riverkeeper with July 7, 2017 Aquatic Macroinvertebrate Bioassessment Study attached
August 9, 2017 Letter from DHEC to SCANA with Aquatic Macroinvertebrate Bioassessment  Attachment Letter from DHEC to SCANA with July 7, 2017 Aquatic Macroinvertebrate Bioassessment attached
July 7, 2017 An Investigation into the Potential Impacts of Coal Tar Contamination on the Invertebrate Community- DHEC Technical Report DHEC’s study of the invertebrate community and evaluation of environmental impacts on the invertebrate populations in the River.
April 28, 2017 Evaluation of Proposed Congaree Capping Alternative for Control of Coal Tar Sediments Southern Environmental Law Center’s Letter and Report evaluating the Capping Alternative for control of Coal Tar Sediments
April 25, 2017 Submittal from SCANA to DHEC Response to DHEC request for additional information regarding cofferdam options.  Includes SCANA's original evaluation from Paul C. Rizzo Associates, Inc. of coffer dam options for the Congaree River.
April 7, 2017 Letter from DHEC to SCE&G Re:  Surface Water Monitoring Results
DHEC's request for SCE&G to submit a work plan proposing a schedule and locations for regular surface water sampling in the Congaree River.
April 4, 2017 Congaree River Surface Water Sampling Report Analytical results from the DHEC March 2017 surface water sampling.
April 4, 2017 Congaree River Surface Water Sampling Location Map Map illustrating the surface water sampling locations for the DHEC March 2017 sampling event.
March 7, 2017 Congaree River Surface Water Sampling Plan DHEC's work plan for surface water sampling to be conducted in the Congaree River in response to concerns raised at the February 13, 2017 Community Meeting.
January 17, 2017 Letter from SCANA to DHEC Re:  Viability of Large Sandbags
Summarizes the results of the large one-ton sandbag testing activities completed during the Field Demonstration Project (FDP) conducted by SCE&G.  Includes reasons that the large sandbags were determined to not be a viable option for isolating and dewatering areas for subsequent sediment excavation.
October 31, 2016 Letter from US Army Corps of Engineers (USACOE) to South Carolina Department of Natural Resources Engineers Letter Correspondence regarding SCE&G's application for an USACOE permit.  Specifically, the Corps plans to authorize the project under Nationwide Permit 38, Cleanup of Hazardous and Toxic Waste.
September 29, 2016 Letter from SCANA to US Army Corps of Engineers (USACOE) Re:  Joint Application and Pre-Construction Notification (JA-PCN)
Responses to the initial comments provided by the USACOE regarding the September 22, 2016 submittal of the JA-PCN.
September 22, 2016 Submittal from SCANA to US Army Corps of Engineers (USACOE) Re:  Joint Application and Pre-Construction Notification - Individual Permit Phase 2 - Modified Removal Action - Sediment Capping Project
SCE&G's Joint Federal and State Application for Activities Affecting Waters of the United States or Critical Areas of the State of South Carolina.  Includes documents in support of an Individual Permit Application.
August 16. 2016 Letter from DHEC to SCANA Re:  SCE&G Congaree River Sediments, Columbia SC
Correspondence requesting that SCE&G pursue Engineering Evaluation/Cost Analysis Alternative 3 - Sediment Capping and Institutional Controls instead of the removal alternative previously envisioned.
July 12, 2016 Submittal from SCANA to DHEC Re:  Field Demonstration Project (FDP) - Documentation Report
SCANA's Documentation Report on the FDP submitted to DHEC for review and approval.  Includes a detailed description of site preparation activities, permits and approvals, regulatory interactions, subcontractors and the findings of the completed field work in support of the FDP.
September 2, 2015 Submittal from SCANA to DHEC Re:  Field Demonstration Project Work Plan
DHEC's approval of the Field Demonstration Project Work Plan.
July 17, 2015 Submittal from SCANA to DHEC Re:  Field Demonstration Project (FDP) - Work Plan
SCANA's FDP Work Plan submitted to DHEC for review and approval of a pilot test to try an alternate removal approach by building a temporary dam using sandbags to allow for excavation in the river.
April 30, 2015 Letter from APEX Companies, LLC (SCANA Contractor) to US Army Corps of Engineers (USACOE) Re:  USACE Permit - P/N 2011-01356-6NO
Update on the evaluation of cofferdam approaches for the Modified Removal Action.
March 2, 2015 Letter from DHEC to SCE&G Re:  Response to SCANA's February 18, 2015 Status Update - Removal Action Decision
DHEC approval of SCANA's request to move forward with design and permitting of the Modified Removal Action approach as described/proposed in SCANA's February 18, 2015 letter.
February 18, 2015 Letter from SCANA to DHEC Re:  Status Update - Removal Action Decision
Update regarding the Congaree River Sediment Removal project.  Specifically, the problems and concerns identified during review of the current design via the permitting process with regulatory agencies and how the selected removal action alternative would be implemented.  Includes request that DHEC consider a modified approach for completing the removal action.
May 8, 2013 Letter from DHEC to SCE&G Re:  SCE&G Huger Street Former MGP, Columbia SC
Correspondence that DHEC is drafting an Action Memorandum to select Alternative 4 as the official remedy selection for the site.  Request for SCE&G to begin the design and permit process.
January 2013 Final Engineering Evaluation/
Cost Analysis (EE/CA)
Summary of cleanup options evaluated by DHEC.
March 2012 Project Delineation Report Summary of all 5 phases of assessment and discussion of results.
September 2011 Phase IV Delineation Preliminary Findings Assessment Report for Phase 5 Proposed Activities.
August 2011 Phase III Delineation Preliminary Findings Assessment Report for Phase 4 Proposed Activities.
June 2011 Phase II Delineation Summary Assessment Report for Phase 3 Proposed Activities.
December 2010 Phase I Delineation Summary Assessment Report for Phase 2 Proposed Activities.
September 2010 Delineation Work Plan Initial Assessment Work Plan to collect sediment samples in the Congaree River.
August 2002 Voluntary Cleanup Contract Agreement between DHEC and South Carolina Electric & Gas for additional assessment and/or remediation at the site of the former Huger Street Manufactured Gas Plant (MGP)

 

Tags

Pollution