Regulation 61-67: Standards for Wastewater Facility Construction
67.100: General Provisions
67.200: Engineering Reports
- Purpose
- Applicability
- General Requirements
- Additional Conditions Applicable to Specific Categories of Engineering Reports
67.300: Construction Permits
- General Requirements
- Gravity Sewer Lines/Collection Systems
- Pump Stations
- Force Mains
- Alternative Collection Systems
- Wastewater Treatment Facilities
- Pump and Haul Operations
- G.1. Domestic Wastewater
- G.2. Industrial Wastewater
- Unit Contributory Loadings to All Domestic Wastewater Treatment Facilities
67.400: Reliability Classifications
- Purpose
- Applicability
- Sludge Management Requirements
- Reliability Classification I
- Reliability Classification II
- Reliability Classification III